A Change Request is generally needed when a purchase order no longer reflects the expected price, quantity, funding, scope, or remaining balance.

When the change is known in advance

Submit a Change Request before the vendor provides additional goods or services when:

  • The price or quantity will change
  • Additional invoices are expected
  • The scope or funding needs to be updated
  • An unused balance should be canceled or liquidated, depending on whether invoices have been processed
  • The total purchase value may cross a procurement threshold

Cancel or liquidate?

  • Cancel the PO when no invoices have been processed and the order will no longer be used.
  • Liquidate the remaining balance when invoices have been processed but unused funds remain. This is generally completed through a deductive Change Request or, when that is unavailable, the PO Close process.

For more detail, review Keeping POs Clean: Best Practices in RealSource

Consider the total purchase value, including the original PO and the proposed increase—not only the amount of the change.

  • Up to $10,000: Generally within delegated departmental authority
  • Over $10,000 through $200,000: Purchasing review is required, and additional competitive action may be needed
  • Over $200,000: A formal procurement process may be required

Contact Purchasing when a change crosses a threshold, materially expands the original scope, or was not contemplated by the original procurement.

When the invoice has already arrived

Accounts Payable may be able to process a small, unexpected invoice variance within established tolerances. A Change Request may still be appropriate when:

  • Additional invoices are expected
  • The remaining PO balance will be inaccurate
  • The price, quantity, funding, or scope materially changed
  • Purchasing review is required based on the total value

An after-the-fact Change Request may be possible if the PO has not been fully invoiced. AP tolerance should not be used to plan a purchase above the authorized PO amount.