Construction schedule, as planned week of March 10:

  • Bikes locked to the racks outside the Atrium will be removed March 11. The bikes will be cut off and removed.
  • The half wall (east side) of the printer corral will be demolished this week.  This will be NOISY work.
  • Information Services Desk will move to its new, temporary location in the middle of the first floor on Thursday, March 13.
  • By March 14, the perimeter wall for the first floor replacement office suite will be complete.
  • By March 14, the temporary construction wall on the third floor will be complete.
  • The security officer’s desk will move to the temporary entrance on March 20.
  • W. M. Jordan will move the security gates to the temporary entrance during the early morning hours of March 21.
  • New entrance south of Starbucks will be used beginning March 21.
  • The loading dock and “pit” will not be available for deliveries and parking after May 19.